SUCCESS STORY
Pan Pacific Mechanical Delivers Plumbing Systems for Open-Air SoFi Stadium - The First Indoor-Outdoor Stadium & the NFL’s Largest at over 3 Million Feet
Customer Challenge
Pan Pacific was struggling with collaboration across their global outsourced detailing teams. The demanding schedule for project delivery also made their methods of communication insufficient. The advent of COVID in the final stages of construction also presented a challenge as work-from-home requirements went into effect.
Project Goals
The following priority project goals were identified:
1) On-time delivery of the project with zero defects.
2) Streamlined change order process.
3) Ongoing value engineering.
4) Minimized clashes and implications with earlier detection.
Solution
Autodesk BIM Collaborate Pro was invaluable in the management and coordination with the off-shore detailers. Technical support was made available by Autodesk Solution Provider ProGroup to respond as needed and aligned with Pan Pacific's early 5AM start time daily. Training and coordination with the Autodesk Team was also provided as necessary to optimize the use of all software tools deployed.
Business Outcome
The project was delivered on time and profitably. The communication with the other contractors and project owners went very smoothly and the customer was exceptionally pleased with Autodesk Collaborate Pro as a game-changer.
Conclusion
Pan Pacific has described utilizing BIM Collaborate Pro on this project as being a game-changer. Without that tool they would not have been able to coordinate such a large team including detailers around the world.
Project Summary
Delivery Date
2020-08-15
Project Duration
1460 days
Autodesk Solutions
- AutoCAD
- Revit
- Fabrication CADmep
Services Provided
- Virtualization
- System & Software Maintenance
- System Integration
- Configuration & Deployment
Customer Industry
- Architecture, Engineering & Construction